ATCO - 783S Cadotte River

Cadotte River substation is located approximately 2 hours north east of Peace River. This project includes the replacement of 701T transformer at 783S Cadotte River due to the electrical deterioration of the internal windings. Also included in this project is the replacement of the 144 kV fuse assembly due to the jaw misalignment, and additional to this scope is the installation of perimeter ground grid to mitigate the existing touch potential within the sub. Lastly, portions of the perimeter fence will be rebuilt to secure the substation.