• Bear Mountain Hero Banner 1
  • Bear Mountain Hero Banner 2
  • Bear Mountain Hero Banner 3
(image of )

Bear Mountain Wind Farm Substation (AltaGas)

Iconic Power Systems was responsible for the construction of the Bear Mountain Wind Farm substation for AltaGas near Dawson Creek, BC. Iconic Power Systems installed all outdoor substation equipment, 35kV buss duct system, along with 35kV terminations using Phisterer connex connectors, installation of the 35kV GIS switchgear and performed all low voltage wiring and commissioning of the substation.