Cutbank Ridge Project (Encana)

This project consisted of the installation of 138 kV equipment for three substations. Iconic was responsible for the installation and welding of the substation structural steel, installation of the bus work and trenching and installation of the control and LV power cables. Additionally, all wiring and substation lighting was completed. The project also included the installation of the substation fencing, insulation gravel and transformer containment rock.